PROFESSIONAL SUMMARY
Civil/Structural, engineer with more than ten years of professional experience in management, construction, and inspection of buildings, and infrastructure for waterways and transportation systems; extensive experience performing key construction tasks (project management, quality control, surveying, safety, inspection, estimates, bidding, budgets and blueprint review) in the private and public sectors.
EMPLOYMENT HISTORY
METROPOLITAN STEEL, INC. — Structural Steel & Pre-cast Construction, Subcontractor May 2008– Sep 2009
-Increase profitability by assessing and reducing risk, developing construction plans, and maximizing efficiency.
-Plan, schedule and supervision of construction of steel, pre-cast & pre-stressed structures.
-Develop bids and proposals—from inception to estimate preparation and presentation of bid package.
-Design of erection aids & development of erection procedures for Structural Engineer review and field-use.
-Develop and implement surveying procedures to guide and assist field crew(s) during construction.
-Implement guidelines and code(s) established by clients and stakeholders.
CORDECK SALES, INC. — Structural Steel, Pre-cast & Tower Crane Erector, Subcontractor Jan 2008—May 2008
-Implemented Erection Procedures for fast-track, high-rise building construction in metropolitan area(s).
-Developed and implemented surveying procedures to guide and assist field personnel during construction.
-Designed structurally-sound, safe erection aids and temporary supports during a fast-paced project.
-Scheduled personnel and material deliveries to ensure adherence to an aggressive construction schedule.
-Maintained quality, schedule and budget by tracking, documenting and reporting progress to stakeholders.
DELGADO ERECTORS, INC. — Structural Steel & Pre-cast Construction, Subcontractor Aug 2006– Jan 2008
-Directed construction of structural steel and pre-cast/pre-stressed bridges and mid-rise buildings.
-Successfully obtained contracts by performing take-offs, estimates and presenting proposals and bid packages.
-Ensured project compliance with general and special conditions established by clients, including adherence to
building codes, as well as quotas and targets related to specific manpower groups.
-Developed and implemented means & methods to survey and plumb & align structures.
-Reviewed contract documents and proposed value-engineering solutions to Owner(s) and Designer(s).
-Developed and maintained welding procedures and supervised their proper execution.
PARSONS—D.B. STERLIN—Civil & Structural Engineering, Consultants Aug 2005– Aug 2006
-Ensured that new construction of toll highway road(s), bridges, drainage systems, roadway lighting, closed-loop
detection and traffic management systems comply with codes, contract documents, budget and schedule.
-Inspected, documented and reported work & progress of construction of new, toll-highway infrastructure.
-Reviewed, approved or denied requests for change orders, pay-outs and credits associated with contracts.
-Reviewed contract documents and proposed value-engineering solutions to Owner, Designer(s) and Principal(s).
DELGADO ERECTORS, INC— Structural Steel & Pre-cast Construction, Subcontractor Jan 2001– Aug 2003
-Designed Erection Aids and developed Erection Procedures utilized in the construction of structures.
-Managed and supervised the construction of steel and pre-cast/pre-stressed concrete structures.
-Created field drawings, sketches, plans, erection drawings, surveys and as-built(s) of construction.
-Managed contract-related documents (Specifications, Drawings, RFI’s, NCR’s, Change Orders, etc).
KIEWIT—DELGADO, AJV—Elevated Rail & Transit System Infrastructure, GC Jan 2001– Aug 2003
-Integral part of a team that managed the construction of structural systems—caissons, foundations, piers,
elevated infrastructure, numerous stations, support structures and buildings for the Chicago Transit Authority.
-Created field drawings, sketches, plans, erection drawings and as-built(s) to aid field crews.
-Proposed improvements to structural designs through RFI’S—resulting in savings to budget and schedule.
-Implement design changes made by Engineer of Record and maintain reports documenting progress.
-Inspect construction work for contract compliance, direct crews to rectify work when needed and/or submit
documentation that expedites approval of corrective measures or Change Orders.
-Create detailed schedules to coordinate and direct work to be performed without interruption to train schedule.
CITADEL CONSTRUCTION COMPANY—General Construction, Commercial May 1999– Jan 2001
-Developed construction schedules and created status reports, correspondence files and briefings for review.
-Reviewed bids and proposals provided by subcontractors and awarded job(s) to qualified parties based on criteria
-Performed cost-analysis, take-offs, work estimates, budgets, and presented bids/proposals.
DESIGN CONSULTING ENGINEERS---Civil & Structural Engineering, Consultants May 1998– May 1999
-Construction inspection of infrastructure and building projects to verify contract and code compliance.
-Laboratory testing, field inspection and verification of code compliance related to structural steel systems,
reinforced concrete, materials, soils, management of traffic, signaling, and intelligent transportation systems.
PAGE 2
PROJECTS & STRUCTURES
1.- Condell Hospital Cast-in-place concrete & steel, six-story, new building in hospital campus
2.- Edward Hospital Structural steel, four-story, vertical completion expansion to existing structure
3.- Fed-Ex Inter-modal Center Large-scale, distribution center located at O’Hare International Airport
4.- City of Chicago, CPS
(Board of Education)
-Little Village High School, 16.5 acre school campus complex
-S...