Experience:
1- Experience in the Petroleum Projects and Consultations Company (PETROJET) :-
From Nov. 2012 to Jun. 2013:
Title: Quality control engineer
Project Name: West Nile Delta Project (Site Facilities & Site Preparation) – Site D3
Client: BECHTEL
Owner: British Petroleum Company (BP Egypt)
Location: Motobus, Kefer EL-Shekh, Egypt
Project Description: Execution the site facilities and site preparation including the offices unit, stripping, backfilling by clean sand and access roads.
Duties: 1- Quality control of stripping, backfilling and access road works for the project site
2- Handing over civil works to the client.
3- Q/C document control:
a- Submit RFI. , sample approvals, procedures and method statements.
b- Handing over Q/C papers to Client.
c- Handing over AS BUILT drawings to Client.
From Dec. 2011 to Oct. 2012:
Title: Site Manager
Project Name: El-Razzak new villas and mess hall
Client: Khalda Petroleum Company
Owner: Khalda Petroleum Company
Location: Western Desert
Project Description: Execution the next units:
1-One villa for VIP consists of 8 rooms with a bath for each room and big hall on 240 m2.
2-One villa for labors consists of 20 rooms with a bath for each 2 rooms and big hall on 540 m
3-Mess hall will kitchen, butcher room, baker room, dry food store, cold food store, dish washing room and director office on 250 m2
Duties:
• Supervising and coordinate the work of site engineers
• Reviewing the progress reports and daily reports.
• Coordinate the interfacing work with the old underground pipes or cables with the owner representatives.
• Obeying safety instructions for any work item
From Oct. 2010 to Nov. 2011:
Title: Quality control engineer
Project Name: West Nile Delta Project (Site Facilities & Site Preparation) – Site G
Client: British Petroleum Company (BP Egypt)
Owner: British Petroleum Company (BP Egypt)
Location: Idku, El-Behera, Egypt
Project Description: Execution the site facilities and site preparation including the offices unit grubbing, cleaning, stripping, backfilling by clean sand, asphalt roads, access roads, backfilled bund walls and concrete slabs to protect the bund walls.
Duties: 1- Quality control of Grubbing, cleaning, stripping, backfilling and road works for the project site
4- Handing over civil works to the client.
5- Q/C document control:
d- Submit RFI. , sample approvals, procedures and method statements.
e- Handing over Q/C papers to Client.
f- Handing over AS BUILT drawings to Client.
From Jul. 2009 to Sep. 2010:
Title: Quality control engineer
Project Name: WDDM Main Compression Phase VII Project
Client: Brullus Company
Owner: Brullus Company
Location: Idku, El-Behera, Egypt
Project Description: Execution the main compression plant which contains slug catcher unit, HP separators, HIPPS structure, 5 air cooler units, 5 compressor,3 gas turbine generators, generation switch gear building, roads works, concrete cable trenches, pipe racks, concrete paving, underground works & 3 deep drain sumps
Duties: 1- Quality control of reinforced concrete, insulation, backfilling, acrylic paint, concrete finishing, concrete repairs, grouting, joints sealant and fireproofing.
2- Handing over civil works to mechanical department for steel structure erection and equipments installation.
3- Q/C document control:
a- Submit RFI. , sample approvals, procedures and method statements.
b- Handing over Q/C papers to Client.
c- Handing over AS BUILT drawings to Client.
From Aug. 2007 to Jun. 2009:
Title: Civil Superintendent
Project Name: Salam Gas Plant Train3&4 Project
Client: Petrofac International Company
Owner: kalda Petroleum Company
Location: Western Desert, Egypt
Project Description: Execution an extension of old gas plant (train 1 & 2) which consists of train 3 & train 4, water treatment area, 4 gas generator units, power station building, control room extension, 4 condensation tanks and infra structure.
Duties:
• Supervising and coordinate the work of site engineers for civil underground piping works, cable trenches works, concrete road crossings and valve pits for all the site
• Supervising and coordinate the work of site engineers for concrete slabs and finishes leveling in utilities area and Gas Turbine Generators area.
• Reviewing the progress reports and daily reports for my responsibility areas.
• Coordinate the interfacing civil works with the electrical and mechanical works.
• Obeying safety instructions for any work item
From Mar. 2006 to Jul. 2007:
Title: Civil Superintendent
Project Name: El Noubaria for sugar industry & refinery Factory
Client: El Noubaria for sugar industry & Refinery Company
Owner: El Noubaria for sugar industry & Refinery Company
Location: Kilometrage, 92 of Alex.- Cairo Desert Road
Project Description: 20000 m3 excavation, 75000m3 concrete and finishing works for buildings
Duties:
• Supervising and coordinate the work of site engineers for civil works in Washing Unit, Circular Storage, three long vehicles balance units, Five conveyors and Receiving & unloading unit.
• Reviewing the progress reports and daily reports for my responsibility units.
• Coordinate the interfacing civil works with the electrical and mechanical works.
• Obeying safety instructions for any work item
From Mar. 2004 to Feb. 2006:
Title: Site engineer
Project Name: Alexandria fertilizer Plant
Client: UHDE, GmbH
Owner: Alexandria fertilizers Company
Location: Eltabia, Alexandria, Egypt
Project Description: The Project contains all civil works (3200 vibro piles, 2 sub-station buildings, control building, air compressor unit, Urea processing unit, Ammonia processing unit, 2 cooling towers, water treatment area, equipment foundation, pipe racks, Urea bulk store, bagging and loading, Ammonia tank and water intake.
Duties:
• Supervising the execution of 2300 deep piles (vibro type, 22 m length and 60 cm diameter), foundations and ground slabs for the main sub-station, the raft and ground slabs for the Ammonia tank and electrical concrete trenches.
• Reporting the progress and daily reports to the civil works general manager.
•...